Proposed on Tuesday 5th July 2022
Made on Tuesday 5th July 2022
THE CLACKMANNANSHIRE COUNCIL (VARIOUS STREETS, ALLOA) (TEMPORARY ROAD AND FOOTWAY CLOSURES) ORDER 2022
The Clackmannanshire Council has made the above named Order under Section 14 of the Road Traffic Regulation Act 1984 (as amended) on 14th June 2022.
The effect of this Order shall be to close to vehicles and pedestrians:-
The period from 0800 hours on Monday 18th July 2022 until 1615 hours on Friday 7th October 2022, on the section described in Schedules 1 and 2. The temporary closure is required to facilitate main laying and mains connection by SGN.
A copy of the Order, together with a copy of the relative plan, is available below.
Pete Leonard
Strategic Director (Place)
SCHEDULE 1 |
|
List of Roads |
Section of road over which a temporary road closure will be applicable from 0800 hours on Monday 18th July 2022 until 1615 hours on Friday 7th October 2022. |
Hillcrest Drive, Alloa
|
From its junction with A907 Clackmannan Road, southwards for a distance of 25 metres or thereby. |
Diversion |
Via A907, Hawkhill Road and vice versa. |
SCHEDULE 2 |
|
List of Footways |
Section of footway over which a temporary footway closure will be applicable from 0800 hours on Monday 18th July 2022 until 1615 hours on Friday 7th October 2022. |
East Castle Street, Alloa |
From its junction with Forth Crescent westwards then northwards for a distance of 175 metres or thereby. |
Full details of this order can be obtained by downloading the documents listed below in the section marked 'Documents for this Order'.
A copy of the order, together with a copy of the relative plan may also be examined during normal office hours, free of charge at:
5-6-2121 - Various Streets, Alloa - Temporary Road and Footway Closure - Download PDF file
Legal and Governance
Kilncraigs, Greenside Street, Alloa, FK10 1EB
Tel: 01259 450000
Email: customerservice@clacks.gov.uk